Graphic server redundancy is a Polywall Visualizer redundancy function.
To set it up please follow the steps:
1) Open Polywall Visualizer settings on the first (main) controller.
2) Put a tip on Clone mode.
3) Set “1”. It means that this controller is the Primary.
4) Save changes, close settings and restart Visualizer.
5) Open Polywall Visualizer settings on the second controller.
6) Put a tip on Clone mode.
7) Set “2”. It means that this controller is the Secondary.
8) Save changes, close settings and restart Visualizer.
Now it is configured.
All mentioned earlier is related to Visualizer only. In case client has requirements for the full redundancy our partners usually use third party software for Polywall Server Worker components reserving. Two the most popular technologies are VMWare Fault Tolerance and Microsoft HyperV Failover clustering.